MELA SCHOOL 1| ANAIKOT, KAVRE, NEPAL

            *  Click on folders for photos  *

The prototype of MELA school was opened in Anaikot in April 2013. 

The construction took i.a. :

- 3 years of planning and fundraising
- 6 months of construction
- 2 Czech managing architects, a team of 5-13 workmen, several casual volunteers
- 400 bamboo stems
- a truly big pile of loam
- 9 truck of local stone
- 170 bags of cement
- 570m of steel rods
- 3 backpacks full of rope

Construction cost and furniture :       22 330 USD

Construction cost and furniture :                         22 330 USD

Overheads :                                    8 790 USD

Total :                                        31 120 USD

 

Construction managers:                                            Soňa Huberová, Jakub Svatoň

 